After the roof structures were removed, the demolition seemed to go much faster.
This was the photo from 3 October for comparison. That next floor down from the roof only took a week.
UPDATE : In the Daily Express (19 October 2010), it was reported the State Health Director, Dr. Mohd Yusuf Ibrahim said the demolition works was supervised by the Department of Occupational Safety & Health (DOSH) and the Department of Public Works (JKR). The JKR denied their involvement in the demolition. Dr. Yusuf said the demolition will be done manually for the 10th floor to the 7th. The "small cranes" (excavators ) were only used to remove the debris. From the 6th floor down, a crusher crane will be used (so demolition should be faster).